For those who have not done the construction of alumina wear-resistant ceramics, this is a very difficult thing. In fact, it is not difficult to do it in the following order, because alumina ceramics are relatively hard.


The specific construction steps are as follows:


1. The surface of the ceramic liner should be kept clean and dry


2. All metal surfaces that need to be installed with alumina ceramic linings should be supported evenly to prevent deformation during construction


3. Use sandblasting or angle grinder to grind and remove rust on the construction surface of steel plate


4. Mixing glue, in principle, a small amount of time, pay attention to the drying time of the glue, reduce the exposure time of the mixed glue in the air, paste it, and the thickness of the glue coating is about 1-2mm


5. The orientation of the alumina ceramic lining board is based on the principle of not hindering the flow of materials, and the gap between the alumina ceramic lining boards is not greater than 2mm. After sticking, use a rubber hammer to smash it firmly, and put the excess glue on it. remove.


6. Put the iron cap into the small hole of the porcelain plate, and weld it with electric welding (preferably second-protection welding, then apply glue, and finally use the porcelain cap to protect the solder joints (cover the porcelain cap)


7. After the alumina ceramic liner is installed, it is not allowed to move until the glue is fully hardened (full hardening time is 24 hours)


8. If necessary, sand the surface of the alumina ceramic liner after sticking and curing to ensure that the surface is clean, smooth and free of other impurities.