Notes before lining brick installation:
1. The ball mill shall be installed on the base as far as possible. After the cement sets, the adjustment ball mill can run smoothly.
2. Before installing the ball mill, prepare a clean plastic bucket to mix the cement slurry and glue.
3, the light inside the ball mill is not good, it is necessary to connect the lamp wire, in the ball mill to install good lights, work lighting
4. It is necessary to prepare an electric fan, which can blow air from the outside to the inside of the ball mill and ensure good ventilation.
5. Tools: iron hammer, rubber hammer or wood hammer, clay board, gloves.

Classification and selection of adhesives:
1. There are 325# white cement and epoxy resin adhesives.
2, white cement is an inorganic material binder, high temperature resistance, not aging, long service life, low cost, simple and convenient construction, generally adopt wet grinding ball mill, mixing mill, etc. Choose 325# white cement as binder.The disadvantage is that when grinding high purity materials, a small amount of cement will be mixed into the material to form impurities, not easy to remove, generally high purity materials grinding will choose epoxy resin adhesive as the binder.
Unlike cement, a small part of epoxy resin ground into the material will evaporate after heating and will not form new impurities.Epoxy resin adhesive is elastic, in the speed of running relatively fast mill, to a certain extent will cushion the impact of the ball stone against the lining brick, the lining brick formed protection.Epoxy resin adhesive is stronger than cement, usually in the use of dry grinding mill and vibration mill to choose epoxy resin adhesive.Compared with cement, epoxy resin adhesive is easy to aging, the use temperature is generally not more than 150 degrees Celsius, the cost is high, the construction is difficult.

Installation steps:
1, ball mill preparation: any brick or cement residue, welding slag, rust, oil on the surface of the ball mill should be clean, smooth surface, to rough, improve the bonding effect.
2, lining brick installation first choice from the ball mill end face, end face all with straight brick and straight half brick with installation, all lining brick work face to the ball mill, the installation parts should be buckle, the top layer of bricks overlap in the following two bricks on the joint, up and down two rows of bricks to ensure staggered installation.Every installation of a few pieces of lining brick should use rubber hammer or mallet gently beat, let the binder in brick and brick, brick and drum wall evenly filled, ensure bonding quality, strict control brick and brick gap between the brick and brick should be less than 1.5mm.
Began after installing 3, installed on both ends of the cylinder, according to the barrel lining brick volume calculation directly brick brick and the number of rows, according to the second step is to calculate the straight diagonal lines of alternate installation in proportion, in order to make sure the bottom lining brick clingy wall in cylinder body, after the lining brick build by laying bricks or stones good inner diameter to smooth connection, each row along the length direction should use the same specification of straight or oblique brick, brick in the end with a brick, brick joints adjustment to keep every adjacent two rows of staggered brick joints, straight to the last row if brick cannot enter, then install thin brick, crevice water mud off.

Maintenance precautions:
1, soak in water: the temperature is low in winter, the ball mill lining brick after the installation of drying 2 days, to the ball mill filled with water, soaked in water for 7 days, the ball mill water all out, hang for more than 3 days, summer temperature is high, the mill after the installation of 12 hours, cement strength can be filled with water to the mill maintenance.
2. When maintaining the mill, it must cover the mill plug well to prevent other sundries from falling into the mill and causing damage to the inner wall of the mill.
3, when the temperature is low in winter to use the electric stove or sawdust heating method to warm the mill for 24 hours, the next day will be turned over to the other side of the mill for 24 hours, alternating baking, insulation to at least 4 days, you can also choose heating bar heating water.
4, with the adhesive brick, 48 hours after the installation can be directly used.

Brush grinding and other matters needing attention:
To ball mill, ball mill, air foot after 3 days, 1 in water injection to achieve 50% of the ball mill capacity, adding suitable amount of production waste, then add the stone ball mill capacity more than 50% of the ball, to start the ball mill grinding out pulp after 2 hours, the second water reached 70% of the ball mill capacity, grinding down after 2 hours, put the adhesion of waste water after clean, can be put into normal production use.
2. It is strictly prohibited to add only a small amount of pellet stone and water when brushing and grinding to make the grinding run for a long time. In this way, hi will seriously damage the grinding machine, lining brick and pellet stone
3, the ball mill should be installed in the field as far as possible, try to avoid the installation in the manufacturers of the ball mill, to prevent the impact of the ball mill during the hoisting process and transportation process, will cause the impact of the lining brick off.