(1) Formulate according to the requirements of water absorption, aluminum content, strength and so on, and then ball grinding;
(2) Through the filter press and vacuum mechanism to produce inert porcelain balls of the mud strip (during the period to ensure that the moisture is appropriate);
(3) Accurate clay strip cutting (the size of the clay strip is equivalent to the specifications of the inert porcelain ball to be produced), and the extrusion forming process is selected to form it accurately;
(4) The semi-finished product enters the drying room or is naturally dried and loaded into the kiln;
(5) High temperature sintering of inert porcelain ball semi-finished products;
(6) Screening and packaging of finished products.
Among them, the molding methods are mainly semi-isostatic pressing (dry bag method) molding, isostatic pressing molding and rolling molding. The main furnaces are high-temperature tunnel kilns and shuttle kilns.